jhilden has started on expert benchmark analysis. looks great so far
should also look at zenphoto, coppermine, maybe picasaweb
a lot of the upload process is about meta-data
focus needs to be on improving the user experience so it's not so "tech-head" oriented. radical changes are good if needed.
Summer of Code
first offical day of SoC coding was yesterday
phinze
completed intro task and is onto the project
developing a design document for the image tagging feature
want to use terminology and ideas from facebook and flickr to make it easy for users
will start documenting progress on codex.
johndbritton
within 2 weeks should have strings importing from automated builds
drupal doesn't import string translations unless they are already in the system, so code needs to be written to do this. we already have code to generate strings.raw for each module that works
Gallery 1
1.5.8-RC1 and 1.6-alpha4 on May 31st. still on track, will be released with some reviews still open.
bharat has been too busy for reviews, none from beckett, a few from jmullan
waiting on answers to e-mails to -core to resolve several issues, otherwise they won't be fixed
G1 will now log every login attempt
ckdake will use tim_j's private svn to build packages
bharat and valiant imported all the changes into the private 2.2.5 branch. now we need to do some testing before we make packages and announce it to the redistributors
still going to simultaneously do 2.2.5 and 2.3-RC1
GCon
designer is working on t-shirt design (supposedly)
Action Items For Next Week
(bold ones are overdue)
ckdake
get fryfrog/talmdal to help with some release testing
harass bharat about G1 reviews, G2 reviews, SoC
dry run of G2 release process
follow up with fryfrog to do some SQLite testing (from several months ago nightly -> upgrade to latest in SVN)
jmullan
commit icons for paularmstrongdesigns and KSIcons
talmdal
update 2.3 README
tim_j
continue work on G1 security issues including backporting to 1.5 series.
schultmc
update us on corporation status "Real Soon Now"
backport fixes and ask for code reviews or contact the security team to see if 2.2.5 can go in (after end of next friday when school is over and will have more time)
Not at Meeting
alindeman
take over review 341
h0bbel
finish putting together MS testing plan
add more to test matrix for other platforms
beckett
look through integrations page on codex and update (remove obsoletes)
ping phinze for SoC updates
Completed Action items from last week
virshu
add radio buttons for Gallery Plan/Your own plan in digibug module.